Overview
The Rottnest Island Authority engaged Hender Lee to supply and install new conduit access between transformers and remote services, supply and install of pits for Transformer transition and inter-connections. The works were completed while the existing 630KVA Transformer remained energised.
Scope
-
Spare conduit (150mm) to existing Dome Café cable pit north of Bedford Ave toilet block.
-
Spare conduit (150mm) to cable pit located adjacent to Pedal & Flipper brick paved are.
-
Spare conduit (150mm) inter-connect between Transformer transition cable pits.
-
Divert existing Hotel “new” mains conduit to 1000KVA Transformer transition cable pit.
-
Disconnect and remove Events switchboard leaving suitable access to outgoing services.
-
Seal all conduit entries into pits and leave conduits capped with draw ropes installed.
-
Danger tape to be installed as per AS3000:2018
-
Confirm existing buried services prior to excavation
-
GPS and Mapping of all installed asset and trenching
-
Supply of As Constructed drawings
-
Site fencing to protect all open excavations during works
-
Contractor to supply suitable traffic management plan prior to works commencing.