Project Info
Client
Water Corporation
Location
Harvey, WA
Duration
50 Weeks
Harvey Reg Valve Building
Overview
Harvey Reg Valve Building Electrical and Instrumentation Scope. The project value was approximately $250,000.00.
Scope
-
Voltage mitigation
-
Mag flow, chlorine analysers, sampling, instrumentation and pressure transmitters
-
Backup generator
-
Underground power distribution
-
Switchboards, modifications to the existing switchboards, cable ladder and support systems
-
New control room fit out
-
Combined Earthing System
-
FAT testing, commissioning, testing & regional hand over
Challenges
Hender Lee Electrical integrated the new Skader and control systems into the existing operational high pressure main.