Project Info

Client

Georgiou Group

Water Corporation

Location

Kwinana WA

Duration

30 Weeks

Kwinana Sewage Pumping Station

Overview

​

Hender Lee were engaged by Georgiou Group to provide the Electrical Instrumentation, Mechanical and in process commissioning of the new Water Corporation Kwinana area main deep sewage pumping station.

​

Scope

​

  • Mechanical, Electrical and Instrumentation

  • SCADA, 85KW VSDs, Instrumentation & Communications

  • Installation of 2 x 85 KW Flight pumps capacity on Duty cycle of 180L per second

  • The installation of the wet well Stainless Steel Piping, Pumps, and Structural Stainless Steel Work

  • Pressure Transmitters, Mag Flow Units Flow Transmitters, Ultrasonic Level Transmitters and float level indicators indicators

  • Underground LV & HV Power Distribution

  • Switchboards, Motor disconnection cubical's, Instrument & Electrical Cabling, Cable ladder and Support systems

  • Control Room fit out

  • Combined Earthing System

  • Fire detection

  • FAT Testing, Commissioning, Testing & Regional Hand Over

​

Challenges

​

We provided in process final setting and commissioning to pre set and pre calibrated issued instruments that were pre set to incorrect parameters and depths.