Project Info

Client

Guidera O'Connor

Location

Garden Island

Duration

June 2019 - November 2019

GARDEN ISLAND WASTE WATER TREATMENT PLANT AT HMAS STIRLING

E & I WORKS

Overview

The Electrical and Instrumentation Installation works are well underway for the HMAS Stirling Waste Water Treatment Plant on Garden Island as part of the Defence Departments 367million dollar upgrade to the Defence Island Facility.    

Scope

  • More than 100 electrical drives and over 250 field  instruments.

  • MCC Panels , Switchboards, PLC Panels,  Remote I/O Panels, UPS Systems, UPS Distribution Boards

  • The Supply and installation of all cabling LV and ELV  

  • Lighting Systems, Lightning Protection and Earthling systems.

  • Drive connections and Instrumentation

  • Electrical Tie-ins onsite

  • Inspection, Testing, QA ,Commissioning and documentation

Challenges

Hender Lee have provided additional manning resorces to accelerate the delivery of this project within the required time constraints.